Skip to main content

How to calculate restraining quantity in Differential relay during testing







Here I'm providing the equation for calculate restraining quantity in differential relay.

%restrain= I diff setting + (I1 * CT1 error) + (I2 * CT2 error)


I diff setting=Differential setting in relay(ex. 0.2Amp)
I1=Current injected in CT for 1 end relay for testing
I2=Current injected in CT for 2 end relay for testing
Ct error=5%(if injected current <1) OR 15%(if Injected current >=1)

During testing we found Ij1=Ij2, because generally same current is seen during fault bay both end relay

Case-1

Injected current=1Amp,I differ setting=0.2( Assume CT error 15% when Injected current >=1)
%restrain= I diff setting + (I1 * CT1 error) + (I2 * CT2 error)
                   =0.2 +(1 * 0.15) + (1 * 0.15)
                   =0.50
 %restrain =50%(around)


Case-2

Injected current=0.5Amp,I differ setting=0.2 ( Assume CT error 5% when Injected current <1)
%restrain= I diff setting + (I1 * CT1 error) + (j2 * CT2 error)
                   =0.2 +(0.5* 0.05) + (0.5 * 0.05)
                   =0.22
 %restrain =22%(around)

Comments

Popular posts from this blog

Dielectric frequency response (DFR) analysis for moisture measurement in transformer

The dielectric response is a unique characteristic of the particular insulation system. The increased moisture content of the insulation results in a changed dielectric model and, consequently, a changed dielectric response. By measuring the dielectric response of the equipment in a wide frequency range, the moisture content can be assessed and the insulation condition diagnosed. The test connections and modes are the same as used in a traditional transformer insulation power-factor test with the difference being the test is performed at a low voltage, up to 200 Vp-p, and the test is performed at frequencies from 1 kHz to 1μHz .  In this Figure the response curve for oil-impregnated paper. This curve shows a frequency vs. dissipation factor relationship. The higher frequencies display the moisture and aging of the cellulose. Moving from left to right the frequency is reduced and the oil conductivity properties are displayed. In the millihertz range, the ...

Why VLF testing is preferred than conventional DC testing in Diagnostic field?

Testing of cable with conventional method is "DC hipod" testing.A considerable rise in premature failures was observed when polymeric cables (XLPE, EPR, etc.) were introduced into the electric grid and readily being tested with DC. This failure with DC hi-Pot testing is cause of trapped charge within the defects of Insulation due to intense charge migration via Unidirectional DC field When DC test completed and AC supply applied to the cable this charge lead to rapid generation of electrical tree and subsequent failure. VLF testing benefits Potential failures should happen during the actual test so that repairs can be made immediately because test time of VLF testing is more about 15 min to 60 min. Lower power and current requirement for testing which significantly reduced size/weight to allow for a very portable high voltage tester. Both benefits describes briefly as below, Under DC test, test object remain less time under voltage stress than VLF test...

What is Arc Flash Studies?How it is carried out?

In order to identify the specific arc flash hazard at a given piece of equipment within a  given facility, an arc flash study must be performed. Outcome of Arc flash Study? Identify the Arc Flash Protection Boundary (this is the closest approach allowed before PPE must be worn).  arc flash equipment labeling Fault current and coordination analysis  recommendations for PPEs Arc Flash Incident Energy Mitigation Strategies How Arc flash Study carried out? There are several software packages available, similarly to short circuit study and coordination study software packages, to facilitate this analysis by a qualified professional electrical engineer.  Following seven steps to be carried out to done complete Arc flash study of the facility.      1.Gathering all as built documentation of the facility The starting point of study is to accumulate  all documentation like Electrical and earthing drawing etc. If...